Sunday, November 17, 2019

FAT on 2 fully automated, ISO 5 integrated Containment System Isolator lines interfaced with Telstar Lyophilizers was completed in the 1st week of November. Equipment is on-site and is in process of being installed at UI Pharmaceuticals sterile manufacturing facility. The Still, Clean Steam System, and Parts Washer arrived on-site and are in process of qualification and validation. UI Pharmaceuticals looks forward to continued progress with the installation process.